Lagos-Ibadan rail line ready by December- Amaechi

The Minister of Transportation, Rotimi Amaechi, on Wednesday said that the Lagos-Ibadan Standard Guage Rail line should be ready by December.

Amaechi gave the assurance while briefing newsmen in Ibadan, Oyo State capital, at the end of his monthly routine inspection tour of the project.

He started the inspection tour from Ebute-Meta in Lagos, in company of other management staff of the Nigerian Railway Corporation (NRC).

Although the track laying from Ebute-Meta in Lagos to Ibadan in Oyo State, had been completed, the 10 stations along the line were at various levels of completion.

Amaechi said that there had been some improvements and progress in the construction of railways stations along the line.

He said that in some of the 10 stations along the line, the contractor, China Civil Engineering Construction Corporation (CCECC), had finished doors, windows, roofing, flooring, ceiling and lighting.

“Olodo (Station) is just near the completion. At Kajola, what is outstanding is just painting. There are changes at Ebute-Meta. There was an improvement in Kajola, Olodo, and Ebute-Meta, though, not to the extend I expect that it should be.

“They have given us the target; by the end of September, three stations will be ready.

“By the end of October, all the minor stations will be ready, that is six stations. By the end of December, every station will be ready.

“The only one station they (CCECC) are afraid of is Apapa (Station) because they started very late, but I insisted that Apapa should be completed at the same time as the rest,” he said.

The minister said he had assured the contractor of the provision of a task force to help the speedy completion of Apapa Station, adding that he would come to assess the work by the end of September.

He expressed the belief that everything would be put in place before the end of December for movement to passengers and goods.

“Timeline has not changed. Do they meet my target? The answer is No. My target was before we come on Sept.15 for inspection, they should have finished all the minor stations,” he added.

According to him, the excuse given by the contractor was that they didn’t have enough engineers to supervise because of COVID-19 pandemic.

“The same engineers supervising Agbado supervise Agege, that is slowing them down. For me, that is not an excuse.

“I want this work done quickly because I want to move out of this place.

“Their position is that by next week more engineers will be coming; we expect them to isolate for seven days and work will commence. Once, work commences, they will be faster,” the minister added.

On the Oshodi train accident on Monday, Amaechi, described the loss of two lives in the incident as unfortunate, urging motorists to be careful on the rail tracks.

He decried trading activities on the rail tracks, saying that there must be enforcement of the law.

The minister said that government would fence the Lagos corridor to prevent people from trading and playing on the rail tracks.

On the allegation of train attack on Abuja-Kaduna Standard Guage, Amaechi said that the news was not true.

On what next after the project, the minister said that apart from Ibadan to Kano rail line, the ministry had sent to the cabinet for approval of the award of two railway contracts.

According to him, the contracts are Port Harcourt – Onne -Maiduguri; Kano-Maradi Railway and Lagos to Calabar.

NAN

Leave A Reply

Your email address will not be published.